As a water or sewer line is constructed, the engineer certifies
the line is built according to the plans, or if it isn’t exactly as
the
plans specify, the engineer makes the appropriate changes
on the "as built."
These "as builts" are given to the Development
Services Department (DSD) offsite inspector, who then delivers them to
the Water Services Department (WSD) Technical Support. The Technical Support
staff review the plans to make sure we have all the documentation required
in order to map and release the water and sewer lines. This would include
making sure all the land-base documentation is there, making sure the agreement
has been prepared and gone to City Council, making sure we have an Interim
Letter in the file, as well as other necessary documentation. Once all
information is confirmed, the plans are mapped.
Once the "as builts" have been mapped, the DSD
inspector ensures the paving adjustments are complete, and the WSD is notified
that the meters can be released.
Water
Sewer
Copies available at: Water Services Technical Support 602-495-5601
If you have additional question contact Water Services Technical Support division at 602-495-5601.