Plan Review Timeline1

Meter Only

A "meter only" is installed when a water tap already exists at the property line of the lot. Before installation will be processed, the property must be marked with an address, the water meter"meter only" is installed when a water tap already exists at the property line of the lot. Before installation will be processed, the property must be marked with an address, the water meter box must be exposed and set at grade. The meter size will be based on the size of the existing tap box must be exposed and set at grade. The meter size will be based on the size of the existing tap.

METER ONLY
Meter Size Fee
5/8" $  680
3/4" 700
1" 794=
1.5" 1,051
2" 1,203
*3" 3,625
*4" 4,527
*6" 5,331

Fee Effective Date 01/02/2008.

*Cost recovery required

3", 4", 6" AND 8" sizes and relocation to be constructed at cost, with trust deposit in the amount shown. The Developer/contractor must sign cost recovery form. Concrete water vault required for all 3", 4", 6" and 8" meters to be installed by developer/contractor after Water Services Department coordinates installation of services.

If you have additional question contact Water Services Technical Support division at 602-495-5601.



Last modified on 02/18/2009 13:02:24


  Related Links
* Business Expansion and Relocation
* Business Site Selection
* Development Services Department
* Engineering and Architectural Services Department
* Homeowner Projects
* Infill Programs
* Planning Department
* Redevelopment
* Streets Department
* Water Services