Construction has begun! The first phase of construction is the flood control levee between 105th Avenue and Avondale Boulevard (115th Avenue) on the north bank of the Salt/Gila river (right at the confluence). Construction of this piece of the levee was completed in February 2007. The next phase (1B) is scheduled to start in August 2007.
Tentative Future Schedule:
| Phase |
Tentative Start |
Tentative End |
| 1A (levee 105th to Avondale Blvd.) |
November 2005 |
February 2007 |
|
|
|
| 1B (levee Avondale Blvd. to the Agua Fria
River) |
August 2007 |
September 2008 |
|
|
|
| 2B (Emergent wetlands) |
2008 |
2010 |
|
|
|
| 2A (Effluent Pump Station) |
2009 |
2011 |
|
|
|
| 3 (Riparian and open water in river) |
2011 |
2012 |
|
|
|
| 4 & 5 (Gila River Indian Community features) |
To be determined |
To be determined |
|
|
|