Banner for sewer relief project website
Main Page - Sewer Capacity Issues
General Overview - Sewer Capacity Issues

Sewer Capacity
Constraint Zone Map

Sewer Capacity Relief Project Map and Schedule

WSD Temporary Sewer Capacity Procedures
What's New?
Where to find updates
about the issue

Development Issues
Main Page

Related Links
Contact Us

Sewer Relief and Replacement Program
Projects by Priority and Estimated Schedules

Download a pdf file of the Project Schedule (19 KB)* Updated October 17, 2008
See a map of the projects listed below (1 MB) * Updated October 17, 2008

The Water Services Department is committed to completing the sanitary sewer relief program as quickly as possible. We have made significant progress. Some final few projects are experiencing delays due to various issues facing these projects. Issues causing delays on remaining projects include obtaining easements and licenses and cost/contract negotiations with contractors.

This schedule update shows progress made on several projects since the December 2007 update to this website schedule. Of the 32 total projects in this program, 26 are complete. Three projects are currently under construction, and the final three projects are expected to begin construction in the near future.

The estimated program completion date for the remaining projects has been extended to fall 2008.

LIST OF PROJECTS

Project No. 1 - COMPLETED

Project Location: 52 nd Street to Cholla St to Indian Bend Wash

Project Description: Install 2,031 feet of 42-inch sewer line

 

Project No. 2 - COMPLETED

Project Location: East Atlanta Ave – El Dorado Industrial Plaza Three

Project Description: Install 1,426 feet of 15-inch sewer line

 

Project No. 3 - COMPLETED

Project Location (Phase A): Tatum Blvd - Cholla St (west) to Cholla St (east)

Project Location (Phase B): 48 th St - Cholla St (east) to Paradise Village Pkwy South

 

Project No. 4 - COMPLETED

Project Location: Claire Dr : 22 nd St. to Cave Creek Rd./Cave Creek Rd : Claire Dr. to Greenway Rd.

Project Description: Install 3,441 feet of 12-inch sewer line

 

Project No. 5 - COMPLETED

Project Location: 36 th St. N of Sweetwater- Parallel to Emile Zola and along Northbound SR51;
40th St. in Cactus Road

Project Description: Install 1,887 feet of 10, 12, and 21-inch sewer line

 

Project No. 6 - COMPLETED

Project Location: Cactus Road, E of 24 th St. along 32nd St. S of Cactus Road.

Project Description: Install 1,636 feet of 10, 15, and 18-inch sewer line

 

Project No. 7 - COMPLETED

Project Location: Grand Ave. & 35 th Ave. to 39 th Ave. and Clarendon Ave.

Project Description: Install 3,640 feet of 18-inch sewer line

 

Project No. 8 - COMPLETED

Project Location (Phase A): 35th Avenue and Campbell Avenue - capacity restriction lifted

Project Location (Phase B): 27th Avenue and Tuckey Lane to 33rd Avenue and Bethany Home Road

Project Description: Install 7,200 feet of 12 & 15-inch sewer line

 

Project No. 9 - COMPLETED

Project Location: Marshall Ave - 29 th Drive to 35 th Ave.; alley north of Missouri Ave: 35 th Ave to 36 th Drive

Project Description: Install 5,500 feet of 10, 12, and 15-inch sewer line

 

Project No. 10 - COMPLETED

Project Location: Nancy Lane and 41 st Drive

Project Description: Project achieved through other methods

 

Project No. 11 - COMPLETED

Project Location (Phase A): 3rd Drive & Dunlap

Project Location (Phase B): 19th Ave. & Hatcher

Project Location (Phase C): 51st Ave & Bell Road – This phase will be achieved through a development agreement with D.R. Horton Homes

Project Location (Phase D): 40th Street and Stanford Drive - capacity restriction lifted

Project Description: Install 2,252 feet of 15, 18, and 24-inch sewer line

 

Project No. 12 - COMPLETED

Project Location: 7 th St. to 9 th St./Greenway Pkwy to Grovers Ave.

Project Description: Install 4,539 feet of 12 and 24-inch sewer line

 

Project No. 13 - COMPLETED

Project Location: Osborn Road – 48 th Street to 56 th Street

Project Description: Install 5,245 feet of 15-inch sewer line

 

Project No. 14 - Eliminated by Project 13 solution (COMPLETED)

Project Location: 48 th Street – Roosevelt Drive to Thomas Road

 

Project No. 15 - COMPLETED

Project Location: Northern Avenue - 31st to 35th Avenues

Project Description: Install 2,199 feet of 12, 15 and 18-inch sewer line

 

Project No. 16 - COMPLETED

Project Location: 83rd Ave from Indian School to Osborn Road

Project Description: Flow diversion into existing abandoned sewer acquired from the city of Glendale in lieu of constructing of new sewer line.

 

Project No. 17 - COMPLETED

Project Location: McDowell Road and 29 th Avenue

Project Description: Install 1,995 feet of 18 and 24-inch sewer line

 

Project No. 18

Project Location: 71st Drive between Campbell Ave. and Indian School Rd.

Project Description: Install 3,080 feet of 12-inch sewer line

Design Status: COMPLETED

Bid Status: COMPLETED

Construction Status: Scheduled for November 2008 through March 2009

 

Project No. 19

Project Location: 15 th Ave. - Interstate 17 to Hilton Ave. ; Hilton Ave - 15 th Ave. to 11 th Ave. ; Watkins St. : 7 th Ave to 6 th Ave.

Project Description: Install 1,989 feet of 8 and 12-inch sewer line

Design Status: COMPLETED

Bid Status: COMPLETED

Construction Status:Under construction - scheduled for completion February 2009

 

Project No. 20 - COMPLETED

Project Location: From Sweetwater Ave. through easement to Thunderbird and Coral Gables & Sweetwater Ave. drainage ROW between 19 th and 23 rd Avenues

Project Description: Install 2,764 feet of 12, 15 and 18-inch sewer line

 

Project No. 21 - Capacity restriction lifted (COMPLETED)

Project Location: Warner Road and 51 st Street

Project Description: Install 500 feet of 10 and 24-inch sewer line

 

Project No. 22 - COMPLETED

Project Location: Encanto Blvd. between 38th Ave and 39th Avenue

Project Description: Install 825 feet of 8-inch sewer line

 

Project No. 23 - COMPLETED

Project Location: Roosevelt Street and 47 th Avenue

Project Description: Install 840 feet of 12-inch sewer line

 

Project No. 24 - COMPLETED

Project Location (Phase A): 32nd Street and Willetta Street

Project Location (Phase B): N 21 st Ave. / W Maryland Ave./W Glendale Ave./Union Hills Rd.

Project Description: Install 4,574 feet of 10 and 12-inch sewer line

 

Project No. 25 - COMPLETED

Project Location: 39th Avenue and Wilshire Drive

Project Description: Install 80 feet of 8-inch sewer line

 

Project No. 26 - Capacity restriction lifted (COMPLETED)

Project Location: Briarwood Terrace and 18 th Way

Project Description: Install 341 feet of 10-inch sewer line

 

Project No. 27 - COMPLETED

Project Location: 44th Street to 64th Street/Paradise Lane to Greenway Road

Project Description: Install 4,216 feet of 10, 21, and 27-inch sewer line

 

Project No. 28

Project Location: Peoria Avenue – 35th to 39th Avenues & 35th Ave ; 35th Ave. – Peoria to Cactus Road

Project Description: Install 7,646 feet of 15 and 18-inch sewer line

Design Status: COMPLETED

Bid Status: COMPLETED

Construction Status: Under construction - scheduled for completion February 2009

 

Project No. 29 - COMPLETED

Project Location: 15 th Ave. at Grovers Ave.; Union Hills Drive at 10th Street; and 15th Avenue and Anderson Drive

Project Description: COMPLETED

 

Project No. 30 - Capacity restriction lifted (COMPLETED)

Project Location: Alley at Missouri Avenue – West of 35th Avenue

Project Description: Install 269 feet of 12-inch sewer line

 

Project No. 31 - Capacity restriction lifted (COMPLETED)

Project Location: Thomas Road between 47th and 48th Avenues

Project Description: Install 535 feet of 15-inch sewer line

 

Project No. 32 - COMPLETED

Project Location: Holly Street between 50th Lane and 51st Avenue

Project Description: Install 175 feet of 12-inch sewer line

 