The Water Services Department is committed to completing the sanitary sewer relief program as quickly as possible. We have made significant progress. Some final few projects are experiencing delays due to various issues facing these projects. Issues causing delays on remaining projects include obtaining easements and licenses and cost/contract negotiations with contractors.
This schedule update shows progress made on several projects since the December 2007 update to this website schedule. Of the 32 total projects in this program, 26 are complete. Three projects are currently under construction, and the final three projects are expected to begin construction in the near future.
The estimated program completion date for the remaining projects has been extended to fall 2008.
Project No. 1 - COMPLETED
Project Location: 52 nd Street to Cholla St to Indian Bend Wash
Project Description: Install 2,031 feet of 42-inch sewer line
|
| |
Project No. 2 - COMPLETED
Project Location: East Atlanta Ave – El Dorado Industrial Plaza Three
Project Description: Install 1,426 feet of 15-inch sewer line
|
| |
Project No. 3 - COMPLETED
Project Location (Phase A): Tatum Blvd - Cholla St (west) to Cholla St (east)
Project Location (Phase B): 48 th St - Cholla St (east) to Paradise Village Pkwy South
|
| |
Project No. 4 - COMPLETED
Project Location: Claire Dr : 22 nd St. to Cave Creek Rd./Cave Creek Rd : Claire Dr. to Greenway Rd.
Project Description: Install 3,441 feet of 12-inch sewer line
|
| |
Project No. 5 - COMPLETED
Project Location: 36 th St. N of Sweetwater- Parallel to Emile Zola and along Northbound SR51; 40th St. in Cactus Road
Project Description: Install 1,887 feet of 10, 12, and 21-inch sewer line
|
| |
Project No. 6 - COMPLETED
Project Location: Cactus Road, E of 24 th St. along 32nd St. S of Cactus Road.
Project Description: Install 1,636 feet of 10, 15, and 18-inch sewer line
|
| |
Project No. 7 - COMPLETED
Project Location: Grand Ave. & 35 th Ave. to 39 th Ave. and Clarendon Ave.
Project Description: Install 3,640 feet of 18-inch sewer line
|
| |
Project No. 8 - COMPLETED
Project Location (Phase A): 35th Avenue and Campbell Avenue - capacity restriction lifted
Project Location (Phase B): 27th Avenue and Tuckey Lane to 33rd Avenue and Bethany Home Road
Project Description:
Install 7,200 feet of 12 & 15-inch sewer line
|
| |
Project No. 9
- COMPLETED
Project Location:
Marshall Ave - 29 th Drive to 35 th Ave.; alley north of Missouri Ave: 35 th Ave to 36 th Drive
Project Description:
Install 5,500 feet of 10, 12, and 15-inch sewer line
|
| |
Project No. 10 - COMPLETED
Project Location: Nancy Lane and 41 st Drive
Project Description:
Project achieved through other methods
|
| |
Project No. 11 - COMPLETED
Project Location (Phase A): 3rd Drive & Dunlap
Project Location (Phase B): 19th Ave. & Hatcher
Project Location (Phase C): 51st Ave & Bell Road – This phase will be achieved through a development agreement with D.R. Horton Homes
Project Location (Phase D): 40th Street and Stanford Drive - capacity restriction lifted
Project Description: Install 2,252 feet of 15, 18, and 24-inch sewer line
|
| |
Project No. 12 - COMPLETED
Project Location: 7 th St. to 9 th St./Greenway Pkwy to Grovers Ave.
Project Description: Install 4,539 feet of 12 and 24-inch sewer line
|
| |
Project No. 13 - COMPLETED
Project Location: Osborn Road – 48 th Street to 56 th Street
Project Description: Install 5,245 feet of 15-inch sewer line
|
| |
Project No. 14 -
Eliminated by Project 13 solution (COMPLETED)
Project Location: 48 th Street – Roosevelt Drive to Thomas Road
|
| |
Project No. 15 - COMPLETED
Project Location: Northern Avenue - 31st to 35th Avenues
Project Description: Install 2,199 feet of 12, 15 and 18-inch sewer line
|
| |
Project No. 16 - COMPLETED
Project Location:
83rd Ave from Indian School to Osborn Road
Project Description: Flow diversion into existing abandoned sewer acquired from the city of Glendale in lieu of constructing of new sewer line.
|
| |
Project No. 17 - COMPLETED
Project Location: McDowell Road and 29 th Avenue
Project Description: Install 1,995 feet of 18 and 24-inch sewer line
|
| |
Project No. 18
Project Location: 71st Drive between Campbell Ave. and Indian School Rd.
Project Description: Install 3,080 feet of 12-inch sewer line
Design Status: COMPLETED
Bid Status: COMPLETED
Construction Status: Scheduled for November 2008 through March 2009 |
| |
Project No. 19
Project Location: 15 th Ave. - Interstate 17 to Hilton Ave. ; Hilton Ave - 15 th Ave. to 11 th Ave. ; Watkins St. : 7 th Ave to 6 th Ave.
Project Description: Install 1,989 feet of 8 and 12-inch sewer line
Design Status:
COMPLETED
Bid Status: COMPLETED
Construction Status:Under construction - scheduled for completion February 2009 |
| |
Project No. 20 - COMPLETED
Project Location: From Sweetwater Ave. through easement to Thunderbird and Coral Gables & Sweetwater Ave. drainage ROW between 19 th and 23 rd Avenues
Project Description: Install 2,764 feet of 12, 15 and 18-inch sewer line
|
| |
Project No. 21 - Capacity restriction lifted (COMPLETED)
Project Location:
Warner Road and 51 st Street
Project Description:
Install 500 feet of 10 and 24-inch sewer line
|
| |
Project No. 22 - COMPLETED
Project Location: Encanto Blvd. between 38th Ave and 39th Avenue
Project Description: Install 825 feet of 8-inch sewer line
|
| |
Project No. 23
- COMPLETED
Project Location: Roosevelt Street and 47 th Avenue
Project Description: Install 840 feet of 12-inch sewer line
|
| |
Project No. 24 - COMPLETED
Project Location (Phase A): 32nd Street and Willetta Street
Project Location (Phase B): N 21 st Ave. / W Maryland Ave./W Glendale Ave./Union Hills Rd.
Project Description: Install 4,574 feet of 10 and 12-inch sewer line
|
| |
Project No. 25 - COMPLETED
Project Location: 39th Avenue and Wilshire Drive
Project Description: Install 80 feet of 8-inch sewer line
|
| |
Project No. 26 - Capacity restriction lifted (COMPLETED)
Project Location: Briarwood Terrace and 18 th Way
Project Description: Install 341 feet of 10-inch sewer line
|
| |
Project No. 27 - COMPLETED
Project Location: 44th Street to 64th Street/Paradise Lane to Greenway Road
Project Description: Install 4,216 feet of 10, 21, and 27-inch sewer line
|
| |
Project No. 28
Project Location: Peoria Avenue – 35th to 39th Avenues & 35th Ave ; 35th Ave. – Peoria to Cactus Road
Project Description: Install 7,646 feet of 15 and 18-inch sewer line
Design Status: COMPLETED
Bid Status: COMPLETED
Construction Status:
Under construction - scheduled for completion February 2009 |
| |
Project No. 29 - COMPLETED
Project Location: 15 th Ave. at Grovers Ave.; Union Hills Drive at 10th Street; and 15th Avenue and Anderson Drive
Project Description: COMPLETED
|
| |
Project No. 30
- Capacity restriction lifted (COMPLETED)
Project Location: Alley at Missouri Avenue – West of 35th Avenue
Project Description: Install 269 feet of 12-inch sewer line
|
| |
Project No. 31 - Capacity restriction lifted (COMPLETED)
Project Location: Thomas Road between 47th and 48th Avenues
Project Description: Install 535 feet of 15-inch sewer line
|
| |
Project No. 32 - COMPLETED
Project Location: Holly Street between 50th Lane and 51st Avenue
Project Description: Install 175 feet of 12-inch sewer line
|
| |