DISTRICT 8
ORDINANCE G-5443 -
Z-107-08-8 -
26TH STREET AND SOUTHERN AVENUE
Request to hold a public hearing and approve the rezoning for the following item by adopting the Planning Commission's recommendation and the related ordinance.
Application:
Z-107-08-8 - (Appealed by Opposition)
From:
S-2
To:
PUD
Acreage:
2.75
Location:
Southeast corner of 26th Street and Southern Avenue
Proposal:
Planned Unit Development (PUD) to allow landscape contractor's office, indoor storage area, work vehicle and equipment storage, and staging area. Maximum building height of 20 feet.
3/4 Vote Required:
No
Applicant:
Larry Lazarus - Lazarus & Associates, PC
Owner:
Georgio Brothers Partnership (c/o Gothic)
Representative:
Larry Lazarus - Lazarus & Associates, PC
Staff:
Approved, subject to stipulations.
VPC Action:
South Mountain - September 8, 2009 - Approved, subject to stipulations. Vote 11-0
PC Action:
September 9, 2009 - Approved, subject to modified stipulations. Vote 6-1
The following stipulations are subject to discussion at the meeting and the City Council may add, delete, or amend stipulations.
Stipulations
1.
That development shall be in general conformance with the following exhibits as found in the City Council adopted PUD development narrative:
a.
Site Plan (Exhibit 9)
b.
Building Elevations; Sign Plan; Wall Elevations (Exhibit 10)
c.
Landscape Plan (Exhibit 11)
2.
That the approval shall be conditioned upon development commencing within 24 months of the City Council approval of this change of zoning in accordance with Section 506.B.1 of the Phoenix Zoning Ordinance. (For purposes of this stipulation, development shall commence with the issuance of building permits and erection of building walls on site).
3.
That a 10-foot-wide easement for a sidewalk
and landscapingshall be dedicated for the south half of Southern Avenue, as modified or approved by the Development Services Department.
4.
That right-of-way totaling 25 feet shall be dedicated for the north half of Lynne Lane, as approved by the Development Services Department.
5.
That at 15-foot right-of-way triangle shall be dedicated at the northeast corner of 26th Street and Lynne Lane, as approved by the Development Services Department.
6.
That the developer shall construct all streets within and adjacent to the development with paving, curb, gutter, sidewalk, curb ramps, streetlights, landscaping, and other incidentals as per plans approved by the Development Services Department. All improvements shall comply with all Americans with Disabilities Act accessibility standards.