​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​North Phoenix Infrastructure

​​Description

More than 1,100 acres of land bounded by 51st Avenue to I-17 and Loop 303 to State Route 74 is being readied for technology companies. To facilitate construction and operations in the region, new public infrastructure is needed.

This project includes the design and construction of approximately three miles of arterial streets including asphalt, curb, gutter, sidewalk, drainage facilities, street lights and landscaping to support access to the area. The project team met with the Arizona State Land Department to get approval of the draft roadway centerlines developed by Kimley Horn and Associates. Approval will be needed from the Arizona Department of Transportation on the 51st Avenue and Loop 303 centerline alignment and a tie in to a traffic interchange.​

​​Map showing project area bounded by 51st Avenue to I-17 and Loop 303 to State Route 74.

NoteThis project was advertised to contractors as the Northwest Valley Transportation Improvements Project. To avoid any confusion about the location of the project, the Street Transportation Department will refer to the project as North Phoenix Infrastructure in public-facing materials.

Project Highlights

​​In support of the this project, the city is constructing three miles of arterial streets including:

  • Asphalt

  • Curb & Gutter

  • Sidewalks

  • Street lighting

  • Drainage Facilities

  • Landscaping



Anticipated Schedule

Design: January 2021 to Fall 2021

Construction is substantially complete


Street Transportation Title VI and ADA Program
Title VI Notice to the Public and ADA Policy Statement

The City of Phoenix Street Transportation Department hereby gives notice that it is the agency's policy to assure full compliance with Title VI of the Civil Rights Act of 1964, Title II of The Americans with Disabilities Act (ADA) and related statutes and regulations in all program​​​​​​​s and activities. These federal statutes require that no person shall, on the grounds of race, color, or national origin, be excluded from the participation in, be denied the benefits of, or be otherwise subjected to discrimination under any program, activity or service the City of Phoenix Street Transportation Department administers. More information regarding the Title VI program can be found at Street Transportation Title VI and ADA Program or email  STR Title VI Program.​​​



Updated January 2023

​Project Manager

Mario Brown

mario.brown@phoenix.gov​  

Phone number: (602) 262-6553