The City of Phoenix received funding through the Arizona Highway User Revenue (AHUR) for street improvements to 43rd Street from McDowell Road to Palm Lane and along the southwest side of Palm Lane and 43rd Street for approximately 150 feet. The project will enhance safety and mobility for pedestrians in the area.

DescriptionSite Plan for 43rd St, McDowell Rd to Palm LnSite Plan, 43rd St - McDowell to Palm Lane

  • Constructing new four-foot sidewalks where none currently exist on both sides of 43rd Street and along the southwest side of Palm Lane and 43rd Street for approximately 150 feet
  • New ADA ramp at southwest corner of 43rd Street and Palm Lane.
  • New and upgraded street lights
  • New alley entrance
  • Adjust existing driveways to tie in with the new sidewalks
  • Relocating fences, mail boxes and existing utilities

Goals

Improve pedestrian mobility and safety and meet new City of Phoenix standards and guidelines set forth in the Americans with Disabilities Act (ADA).

  • Sidewalks
  • New ADA ramps
  • Driveway Retrofits
  • Street Lights

 

Project Schedule

Design: Completed October 2020

Public Outreach: Construction Notice has been distributed

Construction of original work completed june 2021
Construction has been competed August 2021


Contact:

Tariq Momika
(602) 534-7062
tariq.momika@phoenix.gov

 

Project Number ST87750149