7th Street (Union Pacific Railroad to Jefferson) Rehabilitation Project

​Share this page​

Looking for information related to the 7th Street bridge over the Salt River? Information about that project here​


The city of Phoenix Street Transportation Department is set to begin the rehabilitation project on the 7th Street bridge that goes over the Union Pacific railroad tracks just south of Jefferson Street. The project involves replacing bearing pads so the bridge continues to function as designed. Construction is scheduled to begin in April 2020 with an estimated completion date of fall 2020.

The bearing pads are soft neoprene membranes between the bridge deck and the vertical concrete supports. The pads allow for thermal expansion and contraction of the bridge while preventing direct concrete-to-concrete contact. The bearing pads are underneath the bridge and should be out of sight of the general public. 

 

*NEW* Closure Notice Notice Overnight May 7.pdf

*NEW* Construction Notice - 7th Street and UPRR Bridge Rehabilitation.pdf


 How are these pads replaced?

To replace the pads, the bridge decks on either side of the vertical piers need to be raised about two inches and locked into place.

Why don’t I see any work taking place?

The project is occurring mostly underneath the bridge. The closures occur when the bridge deck is being raised a maximum of 2 inches and then locked into place. Once the deck is locked into place, the road can be opened with cars allowed to move at a reduced speed.

How does this affect vehicles using the bridge?

The maximum allowable speed will be reduced from 35 to 15 while most of the construction is occurring. During the night closures, no vehicles can use the 7th Street Bridge.

What is the duration of the project?

24 weeks

How long will the road closures be?

The longest closures will last eight hours, starting at 10 p.m. and reopening no later than 6 a.m.

Work is planned to occur mostly on weekends.

At what times will the closures occur?

Starting at 10 p.m. on nights when there are no events planned at Talking Stick Resort Arena, Phoenix Convention Center or Chase Field.

What is the detour route?

Southbound traffic on 7th Street

  • Right (west) on Washington
  • Left (south) on 3rd Street to Lincoln
  • Left (east) on Lincoln
  • Right (south) on 7th Street

Northbound traffic on 7th Street

  • Left (west) on Lincoln
  • Right (north) on 4th Street
  • Right (east) on Jefferson
  • Left (north) on 7th Street

Project Hotline for Comments or Questions:

Please call 602-825-3444 or email agranillo@gciaz.com.