    Indian School Road Safety Corridor from 91st Ave to 39th Ave

    ​The ReVISIONing Indian School Road project will make strategic investments in safety measures designed to reduce the number of fatal and serious injury collisions along this arterial road. The city's 2022 Vision Zero Road Safety Action Plan ranked the Indian School Road corridor between 91st and 39th Avenues among the highest crash risk locations within the city.

    The project team will implement proven safety practices to reduce crashes and address safety issues involving pedestrians, bicyclists, people taking transit and drivers. ​Driving, walking or bicycling along Indian School Road will be safer with changes to increase lighting and visibility, create safer places for people to cross the road, installing new traffic signal technology and other improvements detailed on this page.

    Project Details

    The ReVISIONing Indian School Road project is a prioritized project in the Phoenix Road Safety Action Plan (RSAP). The Phoenix RSAP is closely aligned with the City of Phoenix's Transportation T2050 Plan as well as the 2050 Environmental Sustainability Program.

    Map of Indian School Road project area for all phases, ranging from 91st Avenue to 39th Avenue. At various points on the road, the project will include lighting, sidewalks, mid-block crossings, intersectiond, ADA compliance enhancements, medians, transit connections, and a bicycle and pedestrian corridor.
    Map of project area

    Project Features

    • Improve corridor lighting
    • Enhance ADA and pedestrian features
    • Provide bicycle and pedestrian improvements
    • Modernize traffic signals
    • Enhance roadway lighting
    • Install raised medians
    • Add pedectrian crossing signals (HAWKs)
    • Integrate intersection safety improvements
    • Widen and separate sidewalks from vehicular traffic (where possible) 
    • Identify speed mitigation strategies​

    Anticipated Schedule

    This project is in the design phase, during which detailed surveys take place to look at everything above and below ground that must be accounted for in the design. 

    Construction is anticipated to begin in 2027. ​