Project Progress Photos


Damage to the bridge from the fire.

Demolition work began on Monday, March 15.
Progress continued the week of March 15.

Demolition work neared completion the week of March 31.

Progress continued the week of April 5.

Progress continued the week of May 10.

Pier and abutment construction as of May 18

Rebar-reinforced concrete girder to support bridge decking
Crane apparatus that will be used to place the girders to support the bridge decking

191,000 pound girder being lowered into place on June 15, 2021

Precisely aligned girders will support the bridge deck when it is poured next month

The bridge deck was poured on August 6.